|  DP World reports 10.7% gross volume growth in Q2 2017  |    |  Major Ports post combined net surplus of INR 2820 cr in FY 2017  |    |  Odisha sets a target to reach INR 1 lakh cr exports by 2025  |    |  Shapoorji Pallonji Group to spend INR 2,000 cr in Odisha Gopalpur Port  |    |  Air India SATS Airport Services launches mobile app for tracking cargo  |    |  IndiGo & Jet introduce additional flights to Doha, Mumbai from Kozhikode  |    |  Port of Rotterdam registers impressive container throughput rise in H1  |    |  New waterways to connect India with Bangladesh  |    |  Yang Ming to start New Korea-Taiwan-Hong Kong service  |    |  DFC to be commissioned in 2 years  |    |  Domestic air traffic up 20% in June  |    |  No new port in 100 km vicinity of major ports  |    |  IRCTC to install 1,100 water vending machines at railway stations  |    |  Port of Antwerp first half volume increases by 1.9% to 5,143,305 TEU  |    |  Asia-Europe rate falls 2.1% to USD 919 TEU, declines 3.1% to USWC  |    |  Operations at international cargo terminal likely to begin soon  |    |  Haicang Port sees 1H cargo rise 20.7% to 3.12 million TEU  |    |  Bahri gets delivery of 39th VLCC, strengthens its leading position  |    |  Shreyas Shipping & Logistics signs MoA to acquire one Multipurpose vessel  |    |  Businessman to sell 12% stake in CIAL  |   
You are here: Home » National News » Infrastructure» Mumbai Metro third line to be ready by 2020

Mumbai Metro third line to be ready by 2020

08 March 2017 | Mumbai
 

transreproter

Mumbai Metro Rail Corporation (MMRC) Managing Director, Ashwini Bhide, said, the rolling stock for the third line of Mumbai Metro would be ordered in the current year and it would be delivered by 2019. The project is on schedule and is expected to be completed by 2020.

She was addressing the media after inaugurating the first casting yard, that will make concrete rings for lining the Metro tunnels.

The digging of the tunnels with Tunnel Boring Machines (TBM) and placing concrete rings for lining the tunnels happen sequentially.

The 33.5 kilometer (km) third line is expected to cost upwards of INR 20,000 crore, connecting Colaba in South Mumbai with Bandra and SEEPZ area in suburban Mumbai.

The line will have 27 stations out of which 26 will be underground and one would be on the ground. Since almost all the sections of the line are underground, about 40,000 concrete rings will be required for reinforcing the roof of the tunnel.

Bhide said that the line is divided into seven sections or packages, for which six casting yards would be required.

She said that first yard has been inaugurated and simultaneously, work on the other five will also start.

   