|  Cochin Port to commemorate arrival of 1st vessel  |    |  CONCOR to start train service from ICD Agra to Mundra Port  |    |  Korea seaport cargo up 6.6% in April  |    |  CMA CGM launches 2nd loop between India, Mideast &Africa  |    |  Chhattisgarh CM gives nod for Raipur-Vizag highway  |    |  DHL adds another China-Europe rail link  |    |  Jet Airways announces special fares on select domestic routes  |    |  ESL gets Panamax ship of 74,005 DWT  |    |  Allcargo Q4 net slips marginally  |    |  Tata Motors consolidated net profit drops 17%  |    |  CMA CGM rate hikes June 1 on Asian container bound for North Africa  |    |  Yang Ming charters 2 vessels to boost service  |    |  Pacific International Lines to develop integrated logistics park in China  |    |  GMR Hyderabad airport to see INR 2,500 cr capacity expansion  |    |  IndiGo to launch daily non-stop flight between Singapore and Bengaluru  |    |  Railway Minister to launch free wi-fi facility at 28 stations in Konkan  |    |  Asia-Europe rate falls 3.9% to USD924 TEU, drops 8.5% to USWC  |    |  Highway projects worth INR 5 lakh crore planned in 2 yrs  |    |  Rail cargo traffic expands for fourth month  |    |  MPT bags two performance awards  |   
You are here: Home » National News » Infrastructure» Mumbai Metro third line to be ready by 2020

Mumbai Metro third line to be ready by 2020

08 March 2017 | Mumbai
 

transreproter

Mumbai Metro Rail Corporation (MMRC) Managing Director, Ashwini Bhide, said, the rolling stock for the third line of Mumbai Metro would be ordered in the current year and it would be delivered by 2019. The project is on schedule and is expected to be completed by 2020.

She was addressing the media after inaugurating the first casting yard, that will make concrete rings for lining the Metro tunnels.

The digging of the tunnels with Tunnel Boring Machines (TBM) and placing concrete rings for lining the tunnels happen sequentially.

The 33.5 kilometer (km) third line is expected to cost upwards of INR 20,000 crore, connecting Colaba in South Mumbai with Bandra and SEEPZ area in suburban Mumbai.

The line will have 27 stations out of which 26 will be underground and one would be on the ground. Since almost all the sections of the line are underground, about 40,000 concrete rings will be required for reinforcing the roof of the tunnel.

Bhide said that the line is divided into seven sections or packages, for which six casting yards would be required.

She said that first yard has been inaugurated and simultaneously, work on the other five will also start.

   