|  Volvo Auto India to hike prices by up to 2% from April  |    |  CSL to raise INR 1,400-1,500 cr through IPO  |    |  PNC Infratech wins INR 2,720-cr highway projects from NHAI  |    |  Damietta port throughput in January increases 31% to 87,800 TEU  |    |  Global container traffic up 4% in Q4 2016, Port Klang growth leads top 20  |    |  Pawan Hans to start Dilli Darshan chopper rides at INR 2,500  |    |  Port of Virginia is gearing up to handle 13,000-TEU plus ships  |    |  Govt. approves INR 2,029 cr project for JNPT channel expansion  |    |  SpiceJet to fly Kolkata-Dhaka daily  |    |  Dilip Buildcon declared successful bidder for INR 3,269 cr road projects  |    |  Ashok Leyland eyes stronger presence in logistics industry  |    |  APL to launch new CS5 to boost intra-Asia service network  |    |  Ethiopian Airlines adds Ahmedabad to its air cargo services  |    |  IWAI raises INR 340 cr through infrastructure bonds  |    |  Rail freight corridor may lead to lower bidding for road projects  |    |  Move to hike Vallarpadam handling charges opposed  |    |  AirAsia India announces two new routes  |    |  UK port volumes drop 3% in 2016 to total 473.5 mt  |    |  Air India to launch direct flight from Amritsar to Birmingham  |    |  BlackBuck raises nearly INR 476 cr from Sands Capital and existing investors  |   
You are here: Home » National News » Infrastructure» Mumbai Metro third line to be ready by 2020

Mumbai Metro third line to be ready by 2020

08 March 2017 | Mumbai
 

transreproter

Mumbai Metro Rail Corporation (MMRC) Managing Director, Ashwini Bhide, said, the rolling stock for the third line of Mumbai Metro would be ordered in the current year and it would be delivered by 2019. The project is on schedule and is expected to be completed by 2020.

She was addressing the media after inaugurating the first casting yard, that will make concrete rings for lining the Metro tunnels.

The digging of the tunnels with Tunnel Boring Machines (TBM) and placing concrete rings for lining the tunnels happen sequentially.

The 33.5 kilometer (km) third line is expected to cost upwards of INR 20,000 crore, connecting Colaba in South Mumbai with Bandra and SEEPZ area in suburban Mumbai.

The line will have 27 stations out of which 26 will be underground and one would be on the ground. Since almost all the sections of the line are underground, about 40,000 concrete rings will be required for reinforcing the roof of the tunnel.

Bhide said that the line is divided into seven sections or packages, for which six casting yards would be required.

She said that first yard has been inaugurated and simultaneously, work on the other five will also start.

   